How to remove actual / progress from Primavera P6 schedule

We have a Primavera schedule with actual data. Now we want to remove the actual so that we can have an As-Planned schedule.

I will show you how to do it in this article.

We have a simple project with actual data.

How to remove actual progress from Primavera P6 schedule - 1

First we go to Project window -> Calculation tab. Highlight our project, and Check in 2 option :

  • “Link Budget and At Completion for not started activities”
  • “Reset Remaining Duration and Units to Original”

How to remove actual progress from Primavera P6 schedule - 2

Go back to Activity window.

Supposed that we have only Labor resource in this project. Now we will reset Unit and Cost to zero.

Go to Tool -> Global Change. Click New. Select the value as display in this picture.

How to remove actual progress from Primavera P6 schedule - 3

Click on Change button. Primavera will show us the Preview of change.

How to remove actual progress from Primavera P6 schedule - 4

Click on Commit Changes.

Now Resource actual data has been removed.

How to remove actual progress from Primavera P6 schedule - 5

Now we will reset the activity date.

Go to Tool -> Global Change. Click New. Select the value as display in this picture.

How to remove actual progress from Primavera P6 schedule - 6

Click on Change button. Primavera will show us the Preview of change.

How to remove actual progress from Primavera P6 schedule - 7

Click on Commit Changes.

Now Date actual data has been removed.

How to remove actual progress from Primavera P6 schedule - 8

Now we will reset the Data Date.

Click F9 and select Data Date equal to Project Planned Start date.

How to remove actual progress from Primavera P6 schedule - 9

Click Schedule.

Now we have the As-Planned schedule.

How to remove actual progress from Primavera P6 schedule - 10

15 thoughts on “How to remove actual / progress from Primavera P6 schedule

Add yours

  1. If you can show how to update new baseline from old baselines. There are hundreds of activities to update in new baseline. what is the way of doing it ? I’ve tried import/export using excel but the updated activities come out of their WBS

    Like

    1. When you need to update a baseline of a project, you can restore it to become a normal project (In menu Project -> Maintain Baseline). Update it. Then convert it to baseline.

      Like

  2. In my schedules your first step in which we have to select the “link budget” option. It is not getting selected. It in fixed mode where we cant select it. What should i do?

    Like

  3. Hi,
    I am a new starter and faced a problem with changing the start day. I wanted to provide a schedule in P6, the actual date of the project is 30-October-2017, while when I launched the P6 it took the start date as 27-Nov-2017, I tried to change it to 30-October-2017, I failed to do so, need instruction.

    Like

Leave a reply to doduykhuong Cancel reply

Create a website or blog at WordPress.com

Up ↑