We have a Primavera schedule with actual data. Now we want to remove the actual so that we can have an As-Planned schedule.
I will show you how to do it in this article.
We have a simple project with actual data.
First we go to Project window -> Calculation tab. Highlight our project, and Check in 2 option :
- “Link Budget and At Completion for not started activities”
- “Reset Remaining Duration and Units to Original”
Go back to Activity window.
Supposed that we have only Labor resource in this project. Now we will reset Unit and Cost to zero.
Go to Tool -> Global Change. Click New. Select the value as display in this picture.
Click on Change button. Primavera will show us the Preview of change.
Click on Commit Changes.
Now Resource actual data has been removed.
Now we will reset the activity date.
Go to Tool -> Global Change. Click New. Select the value as display in this picture.
Click on Change button. Primavera will show us the Preview of change.
Click on Commit Changes.
Now Date actual data has been removed.
Now we will reset the Data Date.
Click F9 and select Data Date equal to Project Planned Start date.
Click Schedule.
Now we have the As-Planned schedule.
Excellent
LikeLike
Perfect
LikeLike
Most Excellent
LikeLike
If you can show how to update new baseline from old baselines. There are hundreds of activities to update in new baseline. what is the way of doing it ? I’ve tried import/export using excel but the updated activities come out of their WBS
LikeLike
When you need to update a baseline of a project, you can restore it to become a normal project (In menu Project -> Maintain Baseline). Update it. Then convert it to baseline.
LikeLike
That is great!
LikeLike
In my schedules your first step in which we have to select the “link budget” option. It is not getting selected. It in fixed mode where we cant select it. What should i do?
LikeLike
Incase it is disabled then contact to your Primavera admin.
LikeLike
Did you open the project? Make sure the project is opened so that you can select option.
LikeLike
the only thing that you forgot was to run the same type of global change of NON LABOR and equipment
LikeLike
Hi Mr Zoltan,
You’re right. We also need to run Global change for Non labor.
Thank for your sharing.
LikeLike
Hi,
I am a new starter and faced a problem with changing the start day. I wanted to provide a schedule in P6, the actual date of the project is 30-October-2017, while when I launched the P6 it took the start date as 27-Nov-2017, I tried to change it to 30-October-2017, I failed to do so, need instruction.
LikeLike
Hi,
You may need to check the Project Start date and Project Data Date. Make sure it is 30-Oct-2017.
LikeLike
how to prepare revised program from updated baseline???????
LikeLike
Hi Athi,
I got this article. Hope this help : https://doduykhuong.com/2016/09/06/how-to-update-baseline-in-primavera-p6/
LikeLike