Primavera P6: Summarize/Roll up activity duration at WBS level using duration value, not earliest and latest date

By default, Primavera P6 summarizes activity duration at the WBS (Work Breakdown Structure) level by calculating the time span from the earliest Start Date to the latest Finish Date of all activities within that WBS. However, if you prefer to calculate the summary duration by summing the individual durations of all activities, follow these steps: Step 1: Create a User Defined... Continue Reading →

Why does Asterisk (*) appears next to the date in the Start or Finish column when no constraints applied to the activity

Sometimes in Primavera P6, you may notice an asterisk (*) next to the Start or Finish date of an activity, even though no constraints have been applied. What does this mean? Reason for the Asterisk The asterisk indicates that the activity has relationships to external projects. For example: You receive a project file from a... Continue Reading →