By default, when you create a new project in Microsoft Project, it uses a 5-day work week (Monday to Friday). If your project requires a 6-day work week, you can easily adjust the calendar settings. Here's how to do it. Step 1: Review the Current Schedule Let’s start with a simple project using the default 5-day work week.... Continue Reading →
What does “Effort driven” option in Microsoft Project do?
You may have noticed the “Effort driven” option in the Task Details Form and wondered what it actually does. Let’s break it down with a simple example. Example Comparison Task A – Effort Driven OFF This task does not have the Effort driven option enabled. When you assign 2 resources, each resource still has 80... Continue Reading →