Delay Analysis report in Primavera P6: Hide Baseline dates in Delay Event project

We have a report showing Delay Event project and Baseline project. The Baseline project need to show Baseline date so we can compare Baseline date and Impacted date. However we don't need to show Baseline date in Delay Event project  which is meaningless and confusing. However by default, Primavera P6 always shows "something" in Baseline... Continue Reading →

Impacted As-Planned Delay Analysis : Using Primavera P6 to see combined / consolidated effect from some or all delay events

Suppose that the project have 5 delay events. If we need to see a combined effect of delay event 1 and delay event 2, we have to create a new project and insert those delay events. Then if we need to see a combined effect of delay event 1 and delay event 3, we have... Continue Reading →