In Primavera P6, when we use "longest path" option to determine the critical path, the process to determine the longest path is as follows: The longest path activities are determined by reviewing the schedule backwards (starting from the last activity) through the driving relationships; If the relationship between two activities is driving, then both activities... Continue Reading →