1. Purpose of Constraints in Primavera P6 Date restrictions used to reflect project requirements that cannot be built into the network logic.More accurately reflect real-world aspects of a project.Provide added control of a project.Apply to the entire project or to individual activities.Commonly used project-level constraint: Must Finish ByCommonly used activity-level constraint: Start On or AfterNo... Continue Reading →
How Early and Late date are calculated in Start to Start relationship in Primavera P6
In Finish to Start relationship, Primavera calculate Early and Late date base on 2 process Forward Pass (to calculate Early Start and Early Finish) Backward Pass (to calculate Late Start and Late Finish) In Backward Pass, the Late Start of successor (Activity C) will be the base to calculate Late Finish of predecessor (Activity A... Continue Reading →