By default, Primavera P6 summarizes/rolls up activity duration at the WBS level by calculating the period from the earliest Start Date to the latest Finish Date of all activities in that WBS. In case we want to calculate the summary duration by simply adding up the duration of all activities, below are the steps. Go... Continue Reading →