How does Primavera P6 calculate Planned Value Cost for Activities without linear distribution (using Resource Curves or Manual plan) in Earned Value Management

When applying the Earned Value Management (EVM) technique in Primavera P6, one of the key metrics is Planned Value (PV), which is calculated as: Planned Value (PV) = Budget at Completion (BAC) × Schedule % Complete Earned Value (EV) = BAC × Performance % Complete (typically equal to Activity % Complete) Schedule Variance (SV) = EV – PV A positive SV indicates the project is ahead of schedule, making Planned Value a critical... Continue Reading →

Create a website or blog at WordPress.com

Up ↑