By default, when you create a new project in Microsoft Project, it uses a 5-day work week (Monday to Friday). If your project requires a 6-day work week, you can easily adjust the calendar settings. Here's how to do it. Step 1: Review the Current Schedule Let’s start with a simple project using the default 5-day work week.... Continue Reading →
What does “Effort driven” option in Microsoft Project do?
You may wonder what does "Effort driven" option in Task Detail Form do? Here I have 2 tasks. Task A doesn't have Effort driven check. When I assign 2 resources to it, the Work unit for each resource doesn't change (80h for each resource). No matter how many resource I assign, each resource will get... Continue Reading →