Problem: When P6 Professional version 16.2 connect to database SQLite version 16.1, the following notification is shown: When we accept to upgrade a SQLite database from version 16.1 to 16.2, the following error occurs: "SQLite database failed to upgrade" How to fix this problem? Solution: Do not double click on icon to run P6. Instead... Continue Reading →
How to install Primavera P6 Professional 16.1 Stand-alone
After downloading the installation file from Oracle, unzip it. Click on Setup Select "Typical" and click OK Click Install After installation complete, click OK. In Driver type drop-down list, select "P6 Pro Stand-alone (SQLite)", then click Next Select "Add a new standalone database and connection". Click Next Enter new password. For example "admin". Click Next... Continue Reading →