Purpose of EOT It is often incorrectly thought that entitlement to an EOT automatically carries with it an entitlement to compensation for prolongation costs during the period of the EOT. The main effect of an EOT is that the Contractor is relieved of its liability for liquidated damages during the period of the extension and... Continue Reading →
Delay Start-up Insurance to cover Anticipated Profit, Revenue in a Delayed Project
1. What is Delay Start-up Insurance (DSU)? Delay in start-up (DSU) cover is designed to secure the portion of revenue which the owner: Requires to service debt; and Realize anticipated profit. It provides protection against delays arising from physical damage caused by any type of peril included in the relevant material damage cover, i.e. the... Continue Reading →
Typical Delay Analysis Methods in Construction Claims
This article addresses the concepts of several typical delay analysis methods in construction claims. Why do we need Delay Analysis in Construction Claims? Because The Delay Must Affect The Critical Path The Construction Contracts often state that no adjustment to the critical milestones dates or the scheduled completion dates would be made unless the delay... Continue Reading →
Concurrent Delay and Pacing Delay in Construction Project
What is Concurrent Delay? The term “concurrent delay” is commonly used to describe circumstances where owner-caused delays and contractor-caused delays occur at the same time. In true concurrency, the owner and contractor delay events (the cause of delay) both occur at the same time and the delay caused by the delay events start and finish... Continue Reading →
Forensic / Delay Schedule Analysis – Summary Graphic Report in 1 Page
After performing delay analysis work in Primavera P6 or MS Project, we should make a summary graphic report for high-level manager. It would be difficult to get the overview of the analysis with a detail report like the following picture: A simple bar chart or timeline would be more effective and I would like to... Continue Reading →
How to perform Collapsed As-Built / As-Built But-For Schedule Delay Analysis in Primavera P6
Introduction An Collapsed As-Built / As-Built But-For Schedule Delay Analysis (ABBF) is a retrospective CPM schedule delay analysis technique that determines the earliest date that the required project completion activity, or various milestone activities could have been achieved but-for the owner-caused delays that occurred during the project. The amount of owner-caused delay determined from the ABBF Schedule... Continue Reading →
You must be logged in to post a comment.