When assigning a resource to an activity in Primavera P6, the following equation always holds true: Original Duration × Units/Time = Total Units For example:10 days × 8 hours/day = 80 hours This equation is fundamental and must always remain valid, regardless of changes made to the activity. When you modify the duration of an... Continue Reading →