New Feature in Primavera P6 Professional v. 21: Showing Backward/Forward Activity Critical Paths

Primavera P6 Professional version 21 introduces a powerful new feature that allows you to highlight different types of critical paths - making it easier than ever to analyze project schedules from multiple perspectives. Let's walk through how this feature works using a simple project example. How to View Critical Paths When you select to show... Continue Reading →

Displaying multiple projects in Primavera P6

Primavera P6 allows users to view multiple projects simultaneously within the Activity window. In this example, the "Office Building" has been divided into several sub-projects, all organized under an EPS (Enterprise Project Structure) node also named "Office Building". By default, the group settings do not display the EPS title at the top of the activity... Continue Reading →

Primavera P6: Summarize/Roll up activity duration at WBS level using duration value, not earliest and latest date

By default, Primavera P6 summarizes activity duration at the WBS (Work Breakdown Structure) level by calculating the time span from the earliest Start Date to the latest Finish Date of all activities within that WBS. However, if you prefer to calculate the summary duration by summing the individual durations of all activities, follow these steps: Step 1: Create a User Defined... Continue Reading →

Primavera P6: Cannot change Remaining Duration of an Activity

Problem When attempting to change the Remaining Duration of an activity, the value reverts to its original state. Change the Remaining Duration value of an activity Causes & Solutions 1. Expected Finish Constraint If the activity has an Expected Finish constraint, the Remaining Duration is automatically calculated as the time between the Data Date and the Expected Finish date. This prevents manual updates... Continue Reading →

Primavera P6 Constraint: How does it work?

1. Purpose of Constraints in Primavera P6 Date restrictions used to reflect project requirements that cannot be built into the network logic.More accurately reflect real-world aspects of a project.Provide added control of a project.Apply to the entire project or to individual activities.Commonly used project-level constraint: Must Finish ByCommonly used activity-level constraint: Start On or AfterNo... Continue Reading →

How does Primavera P6 determine a driving relationship between activities?

The Driving Relationship is determined based on the Relationship Free Float and the business rules for Driving Relationships. Relationship Free Float Relationship Free Float (Rel FF): The Free Float on the relationship. Calculated as Successor Early Start (assuming a Finish to Start relationship) - Relationship Early Finish on the predecessors' calendar. This field is computed... Continue Reading →

Create a website or blog at WordPress.com

Up ↑