Primavera P6: Hide Blank Activity Code, No Activity Code at the summary band

When grouping activities by Activity Code and the activities are not fully assigned all the Code, the summary band will show "No <<Activity Code name>>" like the following picture. In order to hide these unnecessary words, there is a workaround. Create a new code value in which the description is a blank space or a... Continue Reading →

Primavera P6: Summarize/Roll up activity duration at WBS level using duration value, not earliest and latest date

By default, Primavera P6 summarizes/rolls up activity duration at the WBS level by calculating the period from the earliest Start Date to the latest Finish Date of all activities in that WBS. In case we want to calculate the summary duration by simply adding up the duration of all activities, below are the steps. Go... Continue Reading →

Primavera P6 Constraint: How does it work?

1. Purpose of Constraints in Primavera P6 Date restrictions used to reflect project requirements that cannot be built into the network logic.More accurately reflect real-world aspects of a project.Provide added control of a project.Apply to the entire project or to individual activities.Commonly used project-level constraint: Must Finish ByCommonly used activity-level constraint: Start On or AfterNo... Continue Reading →

How does Primavera P6 determine a driving relationship between activities?

The Driving Relationship is determined based on the Relationship Free Float and the business rules for Driving Relationships. Relationship Free Float Relationship Free Float (Rel FF): The Free Float on the relationship. Calculated as Successor Early Start (assuming a Finish to Start relationship) - Relationship Early Finish on the predecessors' calendar. This field is computed... Continue Reading →

How to perform Collapsed As-Built / As-Built But-For Schedule Delay Analysis in Primavera P6

Introduction An Collapsed As-Built / As-Built But-For Schedule Delay Analysis (ABBF) is a retrospective CPM schedule delay analysis technique that determines the earliest date that the required project completion activity, or various milestone activities could have been achieved but-for the owner-caused delays that occurred during the project. The amount of owner-caused delay determined from the ABBF Schedule... Continue Reading →

Create a website or blog at WordPress.com

Up ↑