In the schedule update of Primavera P6, there are occasionally gaps (empty spaces) between the actual bars and the remaining bars as illustrated in picture below. The reasons and solutions for the issue are described in this article. Reason 1: Primavera P6 schedules and displays the activities on Gantt chart in a very detailed and... Continue Reading →
Primavera P6: Schedule Options – Calculate start-to-start lag from
In Primavera P6 Schedule Options, there are 2 options for "Calculate start-to-start lag from". The purpose of these option is described below. We have a simple project: Activity A has FS relationship with Activity B Activity B has SS relationship with Activity C with a lag value of 2 days. The schedule option in this... Continue Reading →
Concurrent Delay and Pacing Delay in Construction Project
What is Concurrent Delay? The term “concurrent delay” is commonly used to describe circumstances where owner-caused delays and contractor-caused delays occur at the same time. In true concurrency, the owner and contractor delay events (the cause of delay) both occur at the same time and the delay caused by the delay events start and finish... Continue Reading →
Forensic / Delay Schedule Analysis – Summary Graphic Report in 1 Page
After performing delay analysis work in Primavera P6 or MS Project, we should make a summary graphic report for high-level manager. It would be difficult to get the overview of the analysis with a detail report like the following picture: A simple bar chart or timeline would be more effective and I would like to... Continue Reading →
How to perform Collapsed As-Built / As-Built But-For Schedule Delay Analysis in Primavera P6
Introduction An Collapsed As-Built / As-Built But-For Schedule Delay Analysis (ABBF) is a retrospective CPM schedule delay analysis technique that determines the earliest date that the required project completion activity, or various milestone activities could have been achieved but-for the owner-caused delays that occurred during the project. The amount of owner-caused delay determined from the ABBF Schedule... Continue Reading →
How to use an iPad as a second monitor
As a planner, we usually need a second monitor to be more productive. If you have an iPad, you can easily make it a second monitor. Here are the steps: On our iPad, go to App Store and search for "Duet Display". Buy this app (around 20 USD) and install it on our iPad. On... Continue Reading →
How to Install 2 Primavera P6 versions on the same computer
With Primavera P6 version 18, we can easily install the new version 18 and keep the old version (for example version 16) on the same computer. After download version 18 installation source, click on Setup: We will uncheck the option "Replace existing version": Click Install as usual: After finish installation, on the Start menu we... Continue Reading →
Primavera P6 Error: “SQLite Database Failed to Upgrade” When upgrade SQLite database from version 16.1 to 16.2
Problem: When P6 Professional version 16.2 connect to database SQLite version 16.1, the following notification is shown: When we accept to upgrade a SQLite database from version 16.1 to 16.2, the following error occurs: "SQLite database failed to upgrade" How to fix this problem? Solution: Do not double click on icon to run P6. Instead... Continue Reading →
Oracle releases Primavera P6 version 18.8 – What’s New in this version
Oracle has just released Primavera P6 18.8 and here's a look at what's new in Primavera P6 Professional version 18.8: Performance Percent Complete Field Based On Labor Units. The Performance % Complete - Labor Units field shows the percentage of the activity or project planned work that is currently complete as measured by labor units.Calculated as Earned Value Labor Units divided... Continue Reading →
Primavera P6 error when import Microsoft Project XML / Run Update Baseline, Claim Digger
When we import Microsoft Project XML file to Primavera P6 / Run Update Baseline / Claim Digger, an error could appear with Event code: CNFFC- Message: Could not find file \bin\java.exe. Cause: These are scenarios which can cause above error: There is no java.exe file in the \Primavera Common\]ava\jvm\bin directory The JAVA_HOME variable is set to... Continue Reading →
Benefit of using Primavera P6 in Delay Analysis
Primavera P6 software can be very useful in delay analysis work. Some of the benefits are described as follows. 1. Filter which activity affect the critical milestones There could be many delay events happened in a project and each delay event affects certain activities. What are the delay events or activities impacting the critical milestones?... Continue Reading →
Delay Analysis report in Primavera P6: Hide Baseline dates in Delay Event project
We have a report showing Delay Event project and Baseline project. The Baseline project need to show Baseline date so we can compare Baseline date and Impacted date. However we don't need to show Baseline date in Delay Event project which is meaningless and confusing. However by default, Primavera P6 always shows "something" in Baseline... Continue Reading →