Create activity list report include predecessors and successors

Sometimes, you need a report that not only lists activities but also displays their predecessors and successors. Primavera P6 makes this possible through its reporting feature. Here’s how to do it: Step 1: Open the Report Window Go to the Reports window and click the “+” button to create a new report. Step 2: Select... Continue Reading →

Graphing a P6 Resource S-Curve in Excel

Tutorial Files Excel Spreadsheet (Excel 2007+): P6_Scurve_Example.xlsx – 1.5Mb Step 1 – Export Primavera P6 Resource Assignments to Excel Following the steps from our previous tutorial, you now have all the resources and assignments in an Excel sheet. You can modify the primary sheet for better graphical features. Step 2 – How to Use the Data To draw... Continue Reading →

Turn off Auto Compute Actuals for 1 activity

By default, most Primavera P6 projects enable the option: “Recalculate Actual Units and Cost when Duration % Complete changes.” With this setting turned on, whenever you update Duration % Complete, P6 automatically recalculates and updates the Actual Units. This is useful in many cases, as it keeps progress and resource usage aligned. In some situations,... Continue Reading →

Shortcut for moving WBS element

In the WBS window, you can build the entire WBS structure using only the keyboard—which is often much faster than using the mouse. Instead of clicking the “Plus” icon to create a new WBS element, simply press the “Insert” key on your keyboard. Then: Enter the WBS ID Press “Tab”, and enter the WBS name... Continue Reading →