In Primavera we can define Critial activities by 2 option:
There are many reasons why we should choose Longest Path instead of Total Float. One of the reason is that when our project has multiple calendar.
We have 4 activities which have same calendar : Standard 5 day workweek. We use Total Float to calculate Critical path. The result is this:
When I change A1020 activity’s calendar to 1 Day Workweek. We use Total Float to calculate Critical path. The result is this:
You can see it’s wrong critical path.
Now when you choose Longest path option. It will become like this:
Now the critical path is better π
So when you have multiple calendar project, consider to use Longest path option.
This is what I like to call “An Undocumented Feature”. translation; a Primavera Gotchya that will sneak up and getchya when you least expect it. This explains why I have seen some really odd critical paths on my project.
LikeLike
how would you apply this if you’re using MS project since there’s no “Longest Path” option in it?
LikeLike
That’s why I think P6 is more professional than MS Project. You should change to P6 π
LikeLike