Let say we have an activity with 100 days duration and 100 labor units. By default it use Linear spread. It mean, when you reach 5% of duration (5th day in this example) you have 5% of total unit (5 unit in this example). And it spread evenly to that period. So resource spreadsheet will... Continue Reading →
How does “Actual units” spread when you use Resource curve
We have an activity which is applied "Back Loaded" resource curve. When we update progress, the Actual unit will spread just like we plan.