We have an activity which is applied “Back Loaded” resource curve.

When we update the progress, the actual units are distributed in the same pattern as planned.
This means that even during progress updates, the resource allocation follows the back-loaded shape, more resources are consumed toward the later part of the activity rather than at the beginning.