How does “Actual units” spread when you use Resource curve

We have an activity which is applied “Back Loaded” resource curve.

1

When we update the progress, the actual units are distributed in the same pattern as planned.
This means that even during progress updates, the resource allocation follows the back-loaded shape, more resources are consumed toward the later part of the activity rather than at the beginning.