How to define Resource Productivity in Primavera P6 and create schedule

When building a schedule in Primavera P6, you can estimate activity durations based on resource productivity. Here's a step-by-step guide using a concrete example. Example Scenario A construction team can cast 10 m³ of concrete per day (this is the productivity). A foundation requires 100 m³ of concrete. Therefore, the activity duration is calculated as: Now, let’s implement this in Primavera... Continue Reading →

How Early and Late date are calculated in Start to Start relationship in Primavera P6

In a Finish-to-Start (FS) relationship, Primavera P6 calculates Early and Late dates using two main processes: 1. Forward Pass (Calculates Early Start and Early Finish) The Early Start (ES) and Early Finish (EF) of an activity are determined by the earliest possible time the activity can begin and end, based on its predecessor's finish. 2. Backward Pass... Continue Reading →

How to update Baseline in Primavera P6

In project management, a baseline is typically fixed and used to measure performance against the original plan. However, in certain cases—such as significant delays or scope changes—it may be necessary to update the baseline. This guide walks you through two methods to update a baseline in Primavera P6. We have a simple project with an assigned baseline.... Continue Reading →

Automatically update progress in Primavera: The difference between Apply Actuals and Update Progress

When you need to quickly update a project in Primavera P6 (assuming everything is going as planned), there are two options for automatically applying progress: Apply Actuals Update Progress (Progress Spotlight) Both options update activities automatically, but they work differently. Let’s explore. Apply Actuals The Apply Actuals function updates activities that have the Auto Compute... Continue Reading →

How does Retained Logic, Progress Override and Actual Dates in Scheduling Options work?

Primavera P6 provides three key options in the Scheduling Options dialog that control how the software handles Out-of-Sequence Progress: Retained Logic Progress Override Actual Dates Understanding these options is essential for accurate schedule calculations. Let’s explore how each works with an example. Primavera P6 Scheduling Options dialog What is Out-of-Sequence Progress? Out-of-sequence progress occurs when... Continue Reading →

Create a website or blog at WordPress.com

Up ↑