Oracle releases Primavera P6 version 18.8 – What’s New in this version

Oracle has just released Primavera P6 18.8 and here's a look at what's new in Primavera P6 Professional version 18.8: Performance Percent Complete Field Based On Labor Units. The Performance % Complete - Labor Units field shows the percentage of the activity or project planned work that is currently complete as measured by labor units.Calculated as Earned Value Labor Units divided... Continue Reading →

Primavera P6 error when import Microsoft Project XML / Run Update Baseline, Claim Digger

When we import Microsoft Project XML file to Primavera P6 / Run Update Baseline / Claim Digger, an error could appear with Event code: CNFFC- Message: Could not find file \bin\java.exe. Cause: These are scenarios which can cause above error: There is no java.exe file in the \Primavera Common\]ava\jvm\bin directory The JAVA_HOME variable is set to... Continue Reading →

Benefit of using Primavera P6 in Delay Analysis

Primavera P6 is a powerful tool for conducting delay analysis in project management. It offers several features that help identify, evaluate, and present the impact of delays on project schedule. Below are some of the key benefits: 1. Identifying Activities That Impact Critical Milestones In complex projects, multiple delay events may occur, each affecting different... Continue Reading →

What is Expected Finish Date in Primavera P6 used for?

When scheduling a project in Primavera P6, you might notice that the Original Duration of an activity changes unexpectedly. This often happens when the Expected Finish Date is being used. What Is the Expected Finish Date? The Expected Finish Date acts like a constraint in Primavera P6—but only if the scheduling option “Use Expected Finish Dates” is enabled in your project settings. This... Continue Reading →

What is the difference between Activity type: Task Dependent and Resource Dependent in Primavera P6

In Primavera P6, there are two commonly used activity types: Task Dependent and Resource Dependent. The key difference between them lies in how the software determines the calendar used to calculate the activity’s finish date. Task Dependent: P6 uses the Activity Calendar to calculate the finish date. Resource Dependent: P6 uses the Resource Calendar to calculate the finish date. This choice directly impacts... Continue Reading →

Impacted As-Planned Delay Analysis : Using Primavera P6 to see combined / consolidated effect from some or all delay events

Analyzing Combined Delay Events in Primavera P6 Without Creating Multiple Projects In a typical delay analysis scenario, suppose a project experiences five distinct delay events. If we want to analyze the combined impact of Delay Event 1 and Delay Event 2, we traditionally create a new project that includes only those two events. Then, to... Continue Reading →

Create a website or blog at WordPress.com

Up ↑