When creating an activity list for a project in Primavera P6, we often add activities in a non-sequential manner. As a result, the final list of Activity IDs may not follow a clean ascending order, as shown in the example below:
To organize the Activity IDs in ascending order, follow these steps:
- Select all activities in your project.
- Go to the Edit menu and choose Renumber Activity IDs.
- Adjust the Prefix if needed, then click OK.
However, you might notice that the Activity IDs are still not perfectly ascending.
What went wrong?
The issue usually lies in the current sorting settings. To ensure the renumbering works correctly, you need to clear any existing sort criteria before renumbering.
Here’s how:
- Go to the View menu and select Group and Sort.
- Click the Sort button.
- In the Sort dialog, click the Delete button to remove all sort criteria.
- Click OK to apply the changes.
Now, repeat the renumbering process:
- Go to Edit > Renumber Activity IDs, adjust the prefix if necessary, and click OK.
This time, the Activity IDs should be perfectly ascending.






Dear Sir,
I want to know one thing that I have some issues during creating of my baseline schedule … are u doing any kind of online lec’s in which you prepared a baseline schedule(using P6 as a tool) from its beginning to its end like calendar settings to resource loading or generation of cash flow s-curve….
Your Earliest Response is required
Regards, Abubakar
On Tue, Oct 10, 2017 at 5:50 AM, Do Duy Khuong Blog wrote:
> Khuong Do posted: “While making activity list for a project, we usually > have to insert Activity. So the final Activity list don’t have a nice > ascending sequence like below picture: We want all activities ID to be > ascending nicely. So we select all activities, go to menu” >
LikeLike
Hi,
I think I have all of the topic, but they are seperated. You may need to find them.
https://doduykhuong.com/2016/09/06/how-to-update-baseline-in-primavera-p6/
https://doduykhuong.com/2017/03/27/how-to-define-resource-productivity-in-primavera-p6-and-create-schedule/
https://doduykhuong.com/2017/03/07/how-to-assign-resource-resource-loading-make-resource-plan-in-primavera-p6/
https://doduykhuong.com/2016/09/25/how-to-make-a-labor-equipment-mobilization-plan-in-primavera-p6/
LikeLike