How to Change 5 Day Workweek to 7 Day Workweek calendar but keep Project Finish Date unchanged in Primavera P6

After three months of hard work, we completed a schedule using a 5-day workweek calendar, as shown in the image below.

Change 5 Day Workweek to 7 Day Workweek but keep Project Finish Date unchanged in Primavera P6-1

Then came the twist.

The construction team said: “6 March 2018, is the correct project finish date—but we’re using a 7-day workweek, not a 5-day one. Sorry, must’ve been a misunderstanding.”

Wait, what?

Changing the activity calendar affects everything. Normally, if you switch from a 5-day to a 7-day workweek, all activity finish dates shift, as shown in the next image. The new project finish date becomes January 25, 2018.

Change 5 Day Workweek to 7 Day Workweek but keep Project Finish Date unchanged in Primavera P6-2

So how do we keep the original finish date of March 6, 2018, even after changing to a 7-day workweek?

Step 1: Create User Defined Fields

Go to Enterprise > User Defined Fields.

  • Create a field called “Finish 5DW” with data type: Finish Date
  • Create another field called “Start 5DW” with data type: Start Date

Change 5 Day Workweek to 7 Day Workweek but keep Project Finish Date unchanged in Primavera P6-8

Step 2: Save Original Dates

Go to Tools > Global Change.

  • Create a new change named “SaveTo5DW”
  • Set it up to copy the current Start and Finish dates into the new UDFs: Start 5DW and Finish 5DW
  • Click Change to apply

Change 5 Day Workweek to 7 Day Workweek but keep Project Finish Date unchanged in Primavera P6-9

Step 3: Change the Calendar

Change the activity calendar to a 7-day workweek.

  • You can update the first activity, then use the Fill Down function to apply it to the rest.

Change 5 Day Workweek to 7 Day Workweek but keep Project Finish Date unchanged in Primavera P6-5

Step 4: Restore Original Dates

Go to Tools > Global Change again.

  • Create a new change named “LoadFrom5DW”
  • Set it up to copy values from Start 5DW and Finish 5DW back into the Start and Finish fields
  • Click Change to apply

Change 5 Day Workweek to 7 Day Workweek but keep Project Finish Date unchanged in Primavera P6-10

Now, all activity start and finish dates remain the same. Only the durations are recalculated based on the new 7-day calendar. The project finish date stays at March 6, 2018—just as required.

Change 5 Day Workweek to 7 Day Workweek but keep Project Finish Date unchanged in Primavera P6-11

 

4 thoughts on “How to Change 5 Day Workweek to 7 Day Workweek calendar but keep Project Finish Date unchanged in Primavera P6

Add yours

  1. Hi Khuong Do,

    Very interesting and easy method for changing the 5D Calendar to 7D Calendar without changing the finish date of the project. I followed the same as you have shown. It worked exactly as described by you, but unfortunately at the end when i schedule the programme it will change the completion date of the Project and it is neither matching with the 5D Calendar nor with the 7D Calendar. Please confirm that weather I am missing something or really it happens.

    Like

  2. Hi Mr Khuong Do,
    Thank you for your website,

    Could you help me Sir,
    how to create/show in primavera P6 progress last week?
    for example my progress this week is 15%, and progress last week is 10%.
    I want to show the progress last week & progress this week in primavera.

    Thank a lot Sir,

    Ranto

    Like

  3. Mr. Khuong Do,

    I have a Project that is using multiple schedules. I have the start time and finish time the same for all calendars to reduce any time issues I might encounter. Unfortunately, I have a start time displayed on several activities that is what the prior calendar indicated. The first activity has a predecessor that has been actualized and ends at 5pm. The calendar is set for 7am start, 5pm finish. The activity is starting at 8am. I cannot manually change this time to 7am without a constraint, and even with a Start On constraint it continues to show 8am. The Admin preferences are set at “Use assigned calendar to specify the number of work hours for each time period”. I’ve scheduled the Project several times. I’ve F5 refreshed several times. Nothing. The time will not start on the selected calendar start time. Am I missing something?

    Thanks
    Alex

    Like

Leave a reply to rantotumangger Cancel reply

Create a website or blog at WordPress.com

Up ↑