Sometimes in Primavera P6, you may notice an asterisk (*) next to the Start or Finish date of an activity, even though no constraints have been applied. What does this mean?

Reason for the Asterisk
The asterisk indicates that the activity has relationships to external projects.
For example:
- You receive a project file from a colleague and import it into Primavera.
- If the original project had links to activities in another project (external relationships), but that external project was not exported, Primavera displays an asterisk to notify you.
When exporting a project, the external relationships are not included in the XER file, unless the other project is exported too.
How to Remove the Asterisk
To remove the external relationships and clear the asterisk:
Add two columns to your Activity Table:
- External Early Start
- External Late Finish

Delete the external dates from these columns. Reschedule the project.
After rescheduling:
- The asterisk will disappear from the Start and Finish columns.
- The dates will no longer be held by external relationships.

Key Takeaway
The asterisk is a helpful indicator that your activity is linked to an external project. If those links are no longer relevant, clearing the external dates will restore normal scheduling behavior.

HI Dodu,
We would like to get a tutorial of how cost loading is done in Primavera p6 and how to update the progress.
LikeLike
Hi.
Cost is loaded base on resource assignment. I have a article regarding how to quickly assign resource unit. Kindly read it here https://doduykhuong.com/2016/07/08/how-does-top-down-estimation-in-primavera-p6-work/
LikeLike
Amazing
i really suffered in solving it earlier
Thanks for your cooperation and support
Regards
LikeLike
my subcontractor presented a remaining work program (in pdf) where the finish dates contained * with all floats negative.. does this mean that presented programme is not correct?
LikeLike
Hi Arlene,
That means the subcontractor utilised a “constraint” in the finish dates. Usually, a schedule with negative float is only used for certain analysis work such as to show that the project is being late.
LikeLike