Forensic / Delay Schedule Analysis – Summary Graphic Report in 1 Page

After completing delay analysis in Primavera P6 or MS Project, it is important to prepare a concise summary graphic report tailored for high-level management. Detailed reports, such as the one shown below, can be overwhelming and make it difficult to grasp the overall impact of delays at a glance.

Forensic : Delay Schedule Analysis - Summary Graphic Report-1

A simplified visual—such as a bar chart or timeline—offers a clearer and more effective way to communicate key findings. Below are a few sample formats that illustrate this approach.

Summary

Forensic Delay Schedule Analysis - Summary Graphic Report-1, Time Impacted Analysis, As-Built But-For, Collapsed As-Built
Forensic / Delay Schedule Analysis – Summary Graphic Report

Time Impacted Analysis (in Multi Base /Window)

Forensic Delay Schedule Analysis - Summary Graphic Report-2-Time Impact Analysis, Window Analysis
Time Impacted Analysis (in Multi Base /Window)

As-Built But-For / Collapsed As-Built

Forensic Delay Schedule Analysis - Summary Graphic Report-3- As-Built But-For, Collapsed As-Built
As-Built But-For / Collapsed As-Built

You can download PDF file here: Delay Schedule Analysis – Summary Graphic Report

References:

Project data for above sample report is derived from Long International’s Schedule and Delay Analysis Methodologies.

Another Summary Graphic Report of As-Built But-For / Collapsed As-Built Delay Analysis:

You can refer to another Summary Graphic Report of As-Built But-For / Collapsed As-Built Delay Analysis in the following article:

Delay Start-up Insurance to cover Anticipated Profit, Revenue in a Delayed Project

The pdf report can be downloaded in the following link:

Delay Start-up Insurance – Delay Calculation Slides (khuongdo.com)

3 thoughts on “Forensic / Delay Schedule Analysis – Summary Graphic Report in 1 Page

Add yours

Leave a comment

Create a website or blog at WordPress.com

Up ↑