Even Oracle stop supporting the Excel File to import / export data, sometimes we still need to use it.
The latest version it can support is P6 version 8.3
You can download it here:
https://drive.google.com/open?id=0ByHnieTJNwKGRGpoMnJBS25HU28
Even Oracle stop supporting the Excel File to import / export data, sometimes we still need to use it.
The latest version it can support is P6 version 8.3
You can download it here:
https://drive.google.com/open?id=0ByHnieTJNwKGRGpoMnJBS25HU28
Should this download Files be in a specific folder?
Is the Username and Password the same as what I use when I to open Primavera?
Kind Regards – AJ
LikeLike
You can save it in anywhere to use.
Yes, the username and pass is the same as you use for Primavera application.
LikeLike
Looks like it isn’t working on 64 bit windows , is that right?
LikeLike
Looks like it isn’t working on 64 bit windows , is that right?
I am not sure if anyone have a solution for the 64 bit issues
LikeLike
No, it doesn’t support 64 bits application.
LikeLike
I have EPPM v8.3 and Office 2013 (64 bit) on my current system that have Windows 7 (64 bit).
The question is that how can we utilize or get advantages of SDK and where exactly we are suppose to save these files in order to successful integration with P6 database. Moreover, what bit system does this SDK files have 32 or 64bit?
LikeLike
Hi,
Primavera SDK only support Office 32 bit.
Currently I don’t have any installation guide material so you may have to search them on internet.
LikeLike
Hi,
my query might be OOT.
but i having trouble on importing xml file from primavera version 16.1 to primavera version 15.2
the error message :
Microsoft.Practices.Prism.Modularity.ModuleInitializeException: An exception occurred while initializing module ‘CommandLineModule’.
– The exception message was: Exception has been thrown by the target of an invocation.
– The Assembly that the module was trying to be loaded from was:Primavera.Mercury.CommandLineModule, Version=15.2.0.15383, Culture=neutral, PublicKeyToken=null
Check the InnerException property of the exception for more information. If the exception occurred while creating an object in a DI container, you can exception.GetRootException() to help locate the root cause of the problem.
—> System.Reflection.TargetInvocationException: Exception has been thrown by the target of an invocation. —> System.Collections.Generic.KeyNotFoundException: The given key was not present in the dictionary.
at System.Collections.Generic.Dictionary`2.get_Item(TKey key)
at Primavera.Mercury.Importer.ImportService.DoMatchItems[TEntity](EntitySet`1 target, EntitySet`1 source, Dictionary`2 options, Dictionary`2 primaryKeyMapping, ImportProjectSettings importProjectSettings, ILoggerFacade Logger)
at Primavera.Mercury.Importer.ImportService.ImportOneEntitySet[TEntity](EntitySet`1 source, IVenusDataServiceContext targetContext, ImportOptionsList options, ImportProjectSettings importProjectSettings, ILoggerFacade Logger)
— End of inner exception stack trace —
at System.RuntimeMethodHandle.InvokeMethod(Object target, Object[] arguments, Signature sig, Boolean constructor)
at System.Reflection.RuntimeMethodInfo.UnsafeInvokeInternal(Object obj, Object[] parameters, Object[] arguments)
at System.Reflection.RuntimeMethodInfo.Invoke(Object obj, BindingFlags invokeAttr, Binder binder, Object[] parameters, CultureInfo culture)
at Primavera.Mercury.Importer.ImportService.ExecuteImport(EntityContext sourceContext, IVenusDataServiceContext targetContext, ImportOptionsList options, ImportProjectSettings importProjectSettings, ILoggerFacade Logger, Dictionary`2 initialKeyDictionary)
at Primavera.Mercury.CommandLineModule.ExecuteImportExport.DoImport()
at Microsoft.Practices.Prism.Modularity.ModuleInitializer.Initialize(ModuleInfo moduleInfo)
— End of inner exception stack trace —
Failed to load type for module CommandLineModule.
Error was: An exception occurred while initializing module ‘CommandLineModule’.
– The exception message was: Exception has been thrown by the target of an invocation.
– The Assembly that the module was trying to be loaded from was:Primavera.Mercury.CommandLineModule, Version=15.2.0.15383, Culture=neutral, PublicKeyToken=null
Check the InnerException property of the exception for more information. If the exception occurred while creating an object in a DI container, you can exception.GetRootException() to help locate the root cause of the problem.
Appreciate if anyone can share your experience.
thanks
LikeLike
Does anybody need such complicated tool for version 15 or 16 (64bit)? interested in a commercial need for such a tool.
LikeLike
I have EPPM v16.2 and Office 2016(64 bit) on my current system that have Windows 7 (64 bit).
Can you email me the Primavera SDK that supports this version?
Regards;
Doug Galt
778-772-014
dgalt09@gmail.com
LikeLike
Hi Doug,
Primavera SDK only support Office 32 bit. And Oracle stop developing this product so it is impossible to install on 64 bit.
LikeLike
Ok thanks for letting me know.
LikeLike
Could you email me the steps for exporting and importing from p6 to excel the budget qualities and manhours?
LikeLike
Hi. There lots of instruction for export to excel in google. You can refer this http://www.toolboxforplanning.com/2011/03/how-to-import-and-export-excel-data.html?m=1
LikeLike
My email is dgalt09@gmail.com
LikeLike
hey Mr. Khuong Do,
i dowanloaded the files but i can’t configure it with the database i am using PMDB2 database
also in my laptop i have 64 bit do you have the files supporting 64 bit
thanks in advance
LikeLike
Hi.
Primavera SDK only support Office 32 bit. And Oracle stop developing this product so it is impossible to install on 64 bit.
LikeLike