How is the Y-Axis scale determined in the Resource/Activity Usage Profile

When viewing the Resource Usage Profile or Activity Usage Profile in Primavera P6, you may notice that the Y-axis scale is automatically determined by the software. But how exactly is this value calculated?

Let’s break it down.

how-is-the-y-axis-scale-determined-in-the-resource-activity-usage-profile-1

The Y-axis scale depends on the Timescale setting — whether it’s set to weekmonth, or year. Based on this setting, Primavera identifies the maximum value (i.e., the tallest bar) in the chart.

Let’s say we have a simple project, and the highest bar in the usage profile shows 8 hours.

how-is-the-y-axis-scale-determined-in-the-resource-activity-usage-profile-2

Primavera uses the following steps to determine the Y-axis scale:

  1. Calculate a buffer above the max value:
    MaxY = Max × 1.2 = 8 × 1.2 = 9.6 hours
  2. Divide MaxY into 6 intervals:
    Interval size = 9.6 / 6 = 1.6
  3. Round the interval size:
    • Round up the leftmost digit of the interval size.
    • In this case, 1.6 rounds up to 2.
  4. Recalculate the MaxY using the rounded interval:
    New MaxY = 2 × 6 = 12

So, the Y-axis will be labeled in intervals of 2, with a maximum value of 12.

Note:

  • All calculations are done in hours, but the display may convert to days or other time units depending on your settings.
  • The rounding rule is based on the leftmost digit. For example, if the calculated interval is 1200, Primavera will round it up to 2000.

5 thoughts on “How is the Y-Axis scale determined in the Resource/Activity Usage Profile

Add yours

  1. Good to know. By the way, can please let us know; how to adjust cum value in the S curve adjust to 100%. Appreciate your write up on P6.

    Like

  2. Thank you. I never knew how he Y axis was configured. Is Max Value influenced by the number of resources eg What is the Max Value for 6 Laborers on a Year/Quarter timescale.

    Like

Leave a reply to Nancy Cole Cancel reply

Create a website or blog at WordPress.com

Up ↑