In Primavera P6, when we assign resource to activity there is a equation:
Original Duration x Units/Time = Total Units
( 10 days x 8 hours/day = 80 hours )
Now when you change duration, which element will be changed: Units/Time or Total Units?
That’s when Activity Duration Type come in to play.
The above equation must always be true.
The Duration Type rule determines which field has the most importance (value will be fixed). Below is a matrix that identifies which fields are recalculated based on the Duration type.
- If the duration is fixed, P6 will never recalculate the duration.
- If the duration is not fixed, P6 will always recalculate the duration.
Let’s do some exercise to understand it.
Fill in the columns in the table below so that the equation remains true.
Duration Type: Fixed Units/Time
Duration Type: Fixed Units
Duration Type: Fixed Duration & Units
Duration Type: Fixed Duration and Units/Time
Sir i am very thankful to you for the work (Blogs on P6 problems) you are doing for the Primavera learner .
LikeLiked by 1 person
You’re welcome 🙂
LikeLike
Thanks for Sharing this article, it’s really helpful.
Can you also please share Your article for % Complete Type, and how does all go, while updating the Progress
LikeLike