How to use Activity Duration Type in Primavera P6

In Primavera P6, when we assign resource to activity there is a equation:

Original Duration x Units/Time = Total Units

(          10 days        x 8 hours/day = 80 hours         )

How to use Activity Duration Type in Primavera P6-6

Now when you change duration, which element will be changed: Units/Time or Total Units?

That’s when Activity Duration Type come in to play.

The above equation must always be true.

The Duration Type rule determines which field has the most importance (value will be fixed). Below is a matrix that identifies which fields are recalculated based on the Duration type.

How to use Activity Duration Type in Primavera P6-1

  • If the duration is fixed, P6 will never recalculate the duration.
  • If the duration is not fixed, P6 will always recalculate the duration.

Let’s do some exercise to understand it.

Fill in the columns in the table below so that the equation remains true.

Duration Type: Fixed Units/Time

How to use Activity Duration Type in Primavera P6-2

Duration Type: Fixed Units

How to use Activity Duration Type in Primavera P6-3

Duration Type: Fixed Duration & Units

How to use Activity Duration Type in Primavera P6-4

Duration Type: Fixed Duration and Units/Time

How to use Activity Duration Type in Primavera P6-5

Advertisement

3 thoughts on “How to use Activity Duration Type in Primavera P6

Add yours

  1. Thanks for Sharing this article, it’s really helpful.

    Can you also please share Your article for % Complete Type, and how does all go, while updating the Progress

    Like

Leave a Reply to Khuong Do Cancel reply

Please log in using one of these methods to post your comment:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

Create a website or blog at WordPress.com

Up ↑