How does “Level Resources” in Primavera P6 work?

Primavera have a function (called Level Resources) to solve the overload resource problem.

I will explain how does it work in this article.

We have 2 activities which is assigned resource called “Test”.

Level Resources in Primavera P6 - 1

Test can work 8 hour/day. These 2 activities happen at the same time so it will cause Test overload.

Level Resources in Primavera P6 - 2

When you use “Level Resources”, Primavera simply push 1 activity to start later so that Test will not be overload.

You can go to Tool -> Level Resources. And click on Level

Level Resources in Primavera P6 - 3

Now Primavera push activity 2 start date later so Test is no longer overload.

Level Resources in Primavera P6 - 4

How about we want to control what activity to push?

That will be controlled by the “Activity Leveling Priority”. You can show that column in the table.

Level Resources in Primavera P6 - 5

Now I will adjust Level of Activity 2 to be “High”

Level Resources in Primavera P6 - 6

Now if you run “Level resources” again, the Activity 2 will stay, the Activity 1 will be push away.

Level Resources in Primavera P6 - 7

There are lots of option you can configure to control what activity will be push, and how many day it will be push. These are advanced function which I might write in another article.

So the basic concept of Level Resources in Primavera is “push an activity start date later” so that resource will not be overloaded.

4 thoughts on “How does “Level Resources” in Primavera P6 work?

Add yours

  1. The problem in construction industry that management ask to level resources but DO NOT exceed the project finish date I mean target date……in that case how to manage like in the above example….if they say 4th July is the target date and you cannot get the test resource before 30th June…..

    looking forward a good reply..

    Like

Leave a Reply to Rosshan Yadav Cancel reply

Please log in using one of these methods to post your comment:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

Create a website or blog at WordPress.com

Up ↑