How does Resource Shift Calendar in Primavera P6 work?

In Primavera P6 -> Resources window -> Units & Prices tab, there is a selection box called Shift Calendar

How does Resource Shift Calendar in Primavera P6 work - 1

I’ll show how to use it in this article.

The Shift Calendar control the Price/Unit for activity, depend on what time activity start and finish.

For example, we have resource B which has different rate for different shift.

We click on Shift Calendar and select 3-shift Operations.

How does Resource Shift Calendar in Primavera P6 work - 13

How does Resource Shift Calendar in Primavera P6 work - 2

We select Shift 1 and enter 15 $/hour

How does Resource Shift Calendar in Primavera P6 work - 3

We select Shift 2 and enter 10 $/hour

How does Resource Shift Calendar in Primavera P6 work - 4

We select Shift 3 and enter 13 $/hour

How does Resource Shift Calendar in Primavera P6 work - 5

To know what time does the Shift start and finish, we go to Enterprise -> Resource Shift

How does Resource Shift Calendar in Primavera P6 work - 6

Select 3-shift Operations and click Modify

How does Resource Shift Calendar in Primavera P6 work - 7

Now we can see :

  • Shift 1 start at 00:00, finish at 08:00
  • Shift 2 start at 08:00, finish at 16:00
  • Shift 3 start at 16:00, finish at 00:00

How does Resource Shift Calendar in Primavera P6 work - 8

We go to Activity window, let say we have 3 activities which is:

  • Duration is 1 day (8 hours)
  • Calendar : 7-Day Workweek (and 24 hours/day)

How does Resource Shift Calendar in Primavera P6 work - 9

We assign Resource B for all 3 activities.

Now because the start and finish time of each activity is different, the resource will have different Price/Unit.

Activity Excavation start at 00:00, finish at 08:00. The Price/Unit will be Shift 1 : 15 $

How does Resource Shift Calendar in Primavera P6 work - 10

Activity Steel start at 08:00, finish at 16:00. The Price/Unit will be Shift 2 : 10 $

How does Resource Shift Calendar in Primavera P6 work - 11

Activity Concrete start at 16:00, finish at 00:00. The Price/Unit will be Shift 3 : 13 $

How does Resource Shift Calendar in Primavera P6 work - 12

So based on the start and finish time of activity, Primavera will get the right Price/Unit for us.

Advertisement

6 thoughts on “How does Resource Shift Calendar in Primavera P6 work?

Add yours

  1. Hi Do!
    I have a doubt with this.
    I understood that the activities are in a 24h/day calendar. I need to use 3 different crew with 3 different shift in the same activity, but my P6 doesn’t calculate correctly the time nor the total budget. Should I cut the activity on 3 activities and assign every specific crew on each one? Or there is another solution to use only one activity?
    Thanks in advance.
    Nelson HM

    Like

    1. Hi Nelson,
      May be you can try the “one activity” solution. You assign 3 crews (resource) on that activity but you will adjust the Start and Finish time of each resource differently (you can show these column in Resource tab) so that the price is decided by the resource shift.
      I never try this before. Hope that you will succeed 🙂

      Like

  2. Unfortunately to write but I’ve seen all your articles and I tried to understand but none of them were helpful. I guess the problem is with your technic of explanation or smth else.

    Like

  3. I have tried to use the shift calendar to reflect a reduced workforce on nights vs. days…for instance I have 80 persons total with 50 on days and 30 on nights. Activity type is still task driven and activity calendar is 7 x 24, resource calendar is 7 x 24. I’m not tracking cost in my schedule., so I really don’t care about the resource rates. This particular setup does not seem to work as it causes a two week break in work execution. Am I doing something wrong to cause this break or is the tool not set up to use in this fashion???

    Like

  4. Hi Do,

    Thanks for sharing the article.
    I have one question. what is the impact of Shift Calendar (in U & Price tab) on Limit line in Resource Usage Profile? (with the same resource calendar but different shift calendar)

    Thanks,
    Kamran

    Like

Leave a Reply to James Harold Roque Cancel reply

Please log in using one of these methods to post your comment:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

Create a website or blog at WordPress.com

Up ↑